Expert compressor
engineering, built
around your needs
Design, manufacturing, diagnostics and troubleshooting for reciprocating and centrifugal compressors, turbines and pumps. Trusted by OEMs, EPC contractors and plant operators in 30+ countries.
Talk to an engineer
Response within 24 business hours
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

What we do for you

Centrifugal compressors
Aerodynamic design (CFD), mechanical analysis and rotor-dynamics for new machines and revamping of existing ones.
STAGE SELECTION
3D MODEL CFD SIMULATION
FEA STRUCTURAL & MODAL ANALYSiS
Rotor-Dynamics
INLET GUIDE VANE
COMPRESSION UNIT ENGINEERING DESIGN

reciprocating compressors
From a few kW up to 30,000+ kW. Full design with Virtual Prototyping, fatigue analysis and cylinder simulation.
VIRTUAL PROTOTYPING
FATigue analysis
COMPRESSOR CYLINDER FUID-DYNAMIC ANALYSIS

Systems & Packages
Turnkey packaged solutions: engineering, procurement and construction. Lube oil consoles and leak gas recovery systems.
Compression Packages
LUBE OIL CONSOLES
LEAK GAS RECOVERY AND BUFFERING SYSTEMS
How we work
01
Needs assessment
We listen to your problem, collect operational data and define the technical objectives together.
02
Technical proposal
We develop a tailored solution using CFD, FEA and rotor-dynamics simulations.
03
Design & validation
From concept to full detail, with performance verification and structural integrity analysis.
04
Ongoing support
Field engineering, diagnostics and training to maximize reliability and uptime.
SUCCESS STORIES
High Speed Electric Motor Vibrations
During the commissioning on the test bench of a high speed permanent magnet electric motor, severe vibrations were experienced
Results
- A detailed lateral analysis, confirmed by a hammer test, showed that that the first critical speed was within the operating range
- The rotor was redesigned and the shaft stiffened to avoid to be close to a resonance.
Old centrifugal compressor
OEM no longer available. User wanted to extend the operating life of this old unit by upgrading machine monitoring
Results
- Design and implementation of mechanical modifications to house new sensors
- Supply and installation of a new vibration monitoring cabinet, linked to the plant DCS
Short piston rings life
Forced maintenance every 3 months due to fast wearing of PTFE piston sealing elements
Results
- high performance PEEK material suggested
- scheduled temperature monitoring program
Certified standards
API-617
API-618
API-614
ASME VIII
NACE
PED
ATEX
TEMA
"The CST team identified the root cause of a surge problem that had been plaguing us for months. Within four weeks we already had the solution implemented and the machine back in operation."